Pouring concrete


Pete Luna|Leader-News

Workers with Eagle Pass company 4 Ward Construction LLC pour and smooth concrete to create new sidewalks in front of the Uvalde Leader-News office at 110 N. East St. The construction, which is being done in sections across the downtown area, began on July 27 in the area of North High Street. Scheduled to be completed in November, the project is funded by a $250,000 Texas Capital Fund Main Street Improvements Grant from the Texas Department of Agriculture. The city of Uvalde is contributing $75,000 in matching funds toward the total project cost of $325,000.